Three school closure studies nixed by board

Posted

HAMLET — The issues of school closure studies, and converting Ellerbe Middle School into a STEM magnet facility, were again before the Richmond County Board of Education at its Nov. 17 meeting.

At its July 29 work session, the board passed three motions germane to both of those issues. A 5-2 motion approved seeking further information about converting the Ellerbe school into a magnet facility. A 6-1 motion OK'd seeking bids from an independent professional group to study possible closures of four schools: West Rockingham Elementary; Ashley Chapel Education Center; and Cordova and Ellerbe Middle Schools.

A 4-3 motion approved seeking bids for the school closure studies prior to studying EMS as a magnet school.

After consideration, Richmond County Schools Superintendent Dr. Joe Ferrell made the following recommendations: 

  • there should be no independent study of closing Ashley Chapel as such a facility is required under state law; 
  • there should be no independent study of closing West Rockingham Elementary as that would place the system in likely violation of a state law regarding classroom size.

Ferrell recommended no study of closing EMS as at least four school board members are publicly opposed to closing the facility. He also noted that as grant funds for a magnet facility are not currently available, any such study is not feasible.

The superintendent recommended a local system-generated study of the Cordova school, and if closure is advised, then a more thorough formal study should be sought.

On a motion by member Bobbi Sue Ormsby, the board approved amending the July 29 school closure study motion in order to put the superintendent's recommendations into effect. Jerry Ethridge cast the lone dissent.

Steven King, director of maintenance for the school system, advised the board that Bordeaux Construction Co., manager of the L. J. Bell building project, is now considering bids for demolition of the facility. Representatives of Bordeaux are expected to present their recommendations at the December board meeting.

Progress in preparing for demolition has been slowed by studies of possible hazardous materials in the 1952 facility. Currently, demolition is expected to commence by late January 2027.

King also noted progress, or plans, regarding sound systems at Richmond Senior High athletic fields, upgrading the graduation stage, improving the softball field, partial roof replacement on the high school, and alarm system upgrades.

On a motion, the board unanimously approved the Exception Children contract with Public Consulting Group, LLC, in the amount of $150,000 for 2026-2027.

The board approved five amendments to the current schools budget. Eleven school board policies were approved, 6-1, on a motion. Member Daryl Mason cast the dissent, citing his objection to extant language regarding minority small businesses.

The board also approved a resolution officially noting the birth centennial of jazz music great, and Hamlet native, John Coltrane.

Richmond County Board of Education Richmond County Schools closure study construction